Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are working as the project manager in a construction company and is currently working on the construction of a building. The company had just

image text in transcribed

You are working as the project manager in a construction company and is currently working on the construction of a building. The company had just completed the construction of the first floor of the building. The preliminary estimate done by the quantity Surveyor is as shown in Table 2 below. Table 4: Preliminary estimate by Quantity Surveyor Duration 6 days Concrete Quantity 130 m Concrete Cost RM23,000 Workers Quantity 5 Workers Cost RM1000 The project director had queried the concrete work for the first floor and had asked you to verify the material and cost variances for the construction of the first floor of the building. Based on the data obtained from the site supervisor, you have found out that the duration of the concreting for the first floor is 5 days. You have also found that the quantity of concrete used for the first floor is 150m, with the cost of RM25,000 On top of that, you have found that only 4 sub-workers were used during the construction, with the cost of RM850. Prepare your answer to the project director by answering the following questions. a) Calculate the material price and usage variance, and the material cost variance for the concrete work. b) Calculate the labour price and usage variance, and the labour cost variance for the concrete work. c) Determine the status of the material and labour for the concrete work ofthe first floor. d) Explain on why this variance happened and give recommendations onhow to avoid it in future projects

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applied Valuation A Pragmatic Approach

Authors: Clifford S. Ang

1st Edition

3110771748,3110771837

More Books

Students also viewed these Finance questions