You are working in a balanced matrix organization where stakeholder influence is very high and tricky for your project's success. One of the influential and

You are working in a balanced matrix organization where stakeholder influence is very high and tricky for your project's success. One of the influential and high-power stakeholders warns you about various problems that could occur after the implementation of the current project. What should you do in this situation as a part of a stakeholder engagement strategy? 


a. Seek expert judgment about dealing with difficult people


b. Refer to lessons learned from previous projects to avoid the same issues 


c. Apply negotiation skills and political awareness to regain support from this stakeholder 


d. Involve him in team meetings so that he understands the project status



Step by Step Solution

3.30 Rating (150 Votes )

There are 3 Steps involved in it

Step: 1

In balanced matrix organizations power is shared between the project manager and the functional mana... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microbiology A Systems Approach

Authors: Marjorie Kelly Cowan

4th edition

978-007340243, 73402435, 978-0073402437

More Books

Students also viewed these General Management questions

Question

differentiate the function ( x + 1 ) / ( x ^ 3 + x - 6 )

Answered: 1 week ago