You are working on a project that has the following data: BAC = 200 PV = 100 AC = 120 EV =80 Assuming that future
You are working on a project that has the following data: BAC = 200 PV = 100 AC = 120 EV =80
Assuming that future work will be performed at an efficiency rate that considers both the cost and schedule performance indices because project schedule is a factor that impacts future effort, the estimate at completion (EAC) is: A. 250 B. 300 C. 350 D. 345