You are working on a residential construction project. Your total cost estimate for the project is $650,000. You have a contingency reserve of $50,000. The
You are working on a residential construction project. Your total cost estimate for the project is $650,000. You have a contingency reserve of $50,000. The management reserve is $30,000. Your cost baseline is:
$650,000 | ||
$700,000 | ||
$680,000 | ||
Cannot be determine |