You are working on the implementation of smart traffic signals project. The project is about 2 months behind the schedule, at an Actual cost 2.5%
You are working on the implementation of smart traffic signals project. The project is about 2 months behind the schedule, at an Actual cost 2.5% lower than planned. You have delivered a work package EG-017 - Express Green lights installation. You are in which Process Group? a. Monitoring and Controlling b. Initiating c. Planning d. Closing e. Executing
Step by Step Solution
There are 3 Steps involved in it
Step: 1