Question

1 Approved Answer

You are writing the closeout report for a project you are managing. You observe that your project plan called for an $ 8 0 ,

You are writing the closeout report for a project you are managing. You observe that your project plan called for an $80,000 budget, but actual costs totaled $87,500. You note how the majority of extra costs were due to unexpected increases in the price of materials. Which part of your closeout report is the best place to document this information?
1 point
The performance baseline section
The project documentation archive
The outcomes section
The lessons learned section

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions

Question

List what each party is offering and what it hopes to receive. LO.1

Answered: 1 week ago

Question

Date the application was sent

Answered: 1 week ago

Question

B. How effectively are headings used?

Answered: 1 week ago

Question

A. How effectively does the report tell a story?

Answered: 1 week ago