You are writing the closeout report for a project you are managing. You observe that your project plan called for an $ 8 0 ,
You are writing the closeout report for a project you are managing. You observe that your project plan called for an $ budget, but actual costs totaled $ You note how the majority of extra costs were due to unexpected increases in the price of materials. Which part of your closeout report is the best place to document this information?
point
The performance baseline section
The project documentation archive
The outcomes section
The lessons learned section