You dont need to post the excel file just use it to construct your full and correct response please 2. Consider the following project network

image text in transcribedimage text in transcribedimage text in transcribed

You dont need to post the excel file just use it to construct your full and correct response please

2. Consider the following project network for the questions. Activity's time (in days) is given below the name in each activity's box. a. What is the project completion time? b. What is the Latest Finish Time of activity C? c. What is the Earliest Start Time of activity G? d. What is the Slack Time for activity A? e. What is the Slack Time for activity E? f. What is the Critical Path? Problem 1(30%) : Chapter 8 - Problem 2, all parts. Recreate the project network from the problem in the textbook and complete it using Excel functions. Include all your answers in a textbox. Compile vour answers in Microsoft Excel and submit one file. Each problem must be on a separate worksheet. Do not put multiple homework problems on one worksheet

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Records And Information Management

Authors: William Saffady

4th Edition

1538152541, 978-1538152546

More Books

Students also viewed these General Management questions

Question

Critically evaluate Freuds stages of psychosexual development.

Answered: 1 week ago