You evaluate your critical path and determine that the project will be completed two weeks before management's expected due date. What should you do? A.
You evaluate your critical path and determine that the project will be completed two weeks before management's expected due date. What should you do? A. Delay the project for two weeks. B. Prepare a list of risks that did not occur. C. Pull resources off the critical path to work on non-critical path tasks. D. Increase the scope that will enhance the project and consume two more weeks to complete.