Questions are as follows: 1. Find the crash cost per day. 2. Find the lowest cost to
Fantastic news! We've Found the answer you've been seeking!
Question:
Questions are as follows:
1. Find the crash cost per day.
2. Find the lowest cost to complete the project in 10 days.
Note: Assume partial crashing.