You have a project that is scheduled to be completed in 10 days at a budgeted cost of R100, 000. At the end of day
- You have a project that is scheduled to be completed in 10 days at a budgeted cost of R100, 000. At the end of day 6 you do an analysis and you determine the job is 70% complete and you have spent R 65,000.
Assumptions:
For the EAC, this report uses the EAC formula of EAC = BAC/CPI, which is one of the EAC formulas; assuming the current trend of the cost performance will be typical of the project going forward.
- What is the projects earned value at day 6?
- What is the projects budget at completion?
- Is the project ahead, behind schedule or on time?
- Is the project expected to complete on budget, under or over budget?
- What is the projects SPI at day 6?
- What is the projects CPI at day 6?
- What is the Estimate to Completion?
- What is the Estimate at Completion?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started