You have a project that is scheduled to be completed in 10 days at a budgeted cost of R100, 000. At the end of day

  1. You have a project that is scheduled to be completed in 10 days at a budgeted cost of R100, 000. At the end of day 6 you do an analysis and you determine the job is 70% complete and you have spent R 65,000.

Assumptions:

For the EAC, this report uses the EAC formula of EAC = BAC/CPI, which is one of the EAC formulas; assuming the current trend of the cost performance will be typical of the project going forward.

  1. What is the projects earned value at day 6?
  2. What is the projects budget at completion?
  3. Is the project ahead, behind schedule or on time?
  4. Is the project expected to complete on budget, under or over budget?
  5. What is the projects SPI at day 6?
  6. What is the projects CPI at day 6?
  7. What is the Estimate to Completion?
  8. What is the Estimate at Completion?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Explain how to handle conflict effectively.

Answered: 1 week ago

Question

What is the use of bootstrap program?

Answered: 1 week ago

Question

What is a process and process table?

Answered: 1 week ago

Question

What is Industrial Economics and Theory of Firm?

Answered: 1 week ago