You have already spent $10M on a project. You need another $5M to complete the project. Once completed the project will earn revenue minus operating
You have already spent $10M on a project. You need another $5M to complete the
project. Once completed the project will earn revenue minus operating cost equal
to $7.5M. Should you complete the project? What if the revenue minus operating
cost is $2.5M?