Question
You have been appointed as the project manager for a shopping centre construction project. The area in which you are building is prone to excessive
You have been appointed as the project manager for a shopping centre construction project. The area in which you are building is prone to excessive rain and occasional flooding. You are working with unfamiliar construction teams. After initial consultation with the local traffic department, it has become clear that it is not satisfied with the road layout as per your building plans. However, it did give the preliminary go-ahead for the project, with the provision that the town engineer and town planner reconsider the plans. To date, all the suppliers you have contacted can supply all the relevant material but cannot guarantee on-time delivery.
Considering this insert, identity any FIVE risks and discuss their sources and impacts.
Advise the project manager on any FIVE techniques that can be utilized in compiling project risks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Identified Risks 1 Excessive Rain and Flooding Risk Source Weather patterns and historical data for the area Impact Potential delays in construction damage to materials and equipment increased costs f...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started