Question
You have been asked to compress your schedule. Your project is 20% under budget but 60% behind schedule. What would be an appropriate compression technique
You have been asked to compress your schedule. Your project is 20% under budget but 60% behind schedule. What would be an appropriate compression technique to use?
Question 8 options:
Fast Tracking | |
Re-Estimating | |
Task Leveling | |
Crashing |
Question 9 (1 point)
The most common type of dependency found in projects is
Question 9 options:
Finish-to-start | |
Finish-to-finish | |
Start-to-finish | |
Start-to-start |
Question 10 (1 point)
If a resource is scheduled to work M-F, 8am-5pm with a 1hr lunch break, on a task whose duration is 35h, for that week the resource would be considered:
Question 10 options:
levelled | |
overallocated | |
incorrectly scheduled | |
underallocated | |
correctly scheduled |
Question 11 (1 point)
A task whose start or finish is driven by another task is called a:
Question 11 options:
Recurring Task | |
Predecessor Task | |
Summary Task | |
Successor Task | |
Semi-flexible constraint |
Question 12 (1 point)
Which of these is NOT an estimating Tool?
Question 12 options:
Top Down | |
Cost Table | |
Analogous | |
Parametric |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started