You have been assigned the task of evaluating two mutually exclusive projects with the following projected free cash flows: Year Project A cash flow Project
You have been assigned the task of evaluating two mutually exclusive projects with the following projected free cash flows:
Year | Project A cash flow | Project B cash flow |
0 | -$100,000 | -$100,000 |
1 | 33,000 | 0 |
2 | 33,000 | 0 |
3 | 33,000 | 0 |
4 | 33,000 | 0 |
5 | 33,000 | 220,000 |
If the appropriate discount rate on these projects is 10%, which project would be chosen and why?