Answered step by step
Verified Expert Solution
Question
1 Approved Answer
You have been given the following information from your project team, and are now ready to develop the project schedule. You have a schedule constraint
You have been given the following information from your project team, and are now ready to develop the project schedule. You have a schedule constraint of finish no later than date 35. Based upon the information in the table below, what is the project float? Activity Predecessor Duration A 3 B A 3 C B 3 D A 7 E D 7 F C,E 3 G E 11 H F,G 4
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started