Question
1 Approved Answer
You have been hired to build 10 machines. Budget = $100,000 Time = 10 weeks After 5 weeks, you have built 4 machines and spent
You have been hired to build 10 machines.
Budget = $100,000
Time = 10 weeks
After 5 weeks, you have built 4 machines and spent $47,500
The Planned value is =
The Actual cost is =
The Earned Value is
The Cost Variance is
The Schedule Variance is
The CPI is
The SPI is
The EAC is
The ETC is
The BCWS is