You have been hired to design User Interface for a Web Site that has five web pages. Each web page is scheduled to take one
You have been hired to design User Interface for a Web Site that has five web pages. Each web page is scheduled to take one day to complete at a cost of $500 per web page. At the end of day 2, you have spent $1100 and 1.5 pages are complete.
How is the project doing in terms of schedule and budget? Show your work in calculating SPI and CPI and how you came to your conclusion.