You have been provided with the following information on your project; schedule performance index (SPI) = 1.1, actual cost (AC) = $77,000, planned value (PV)
You have been provided with the following information on your project; schedule performance index (SPI) = 1.1, actual cost (AC) = $77,000, planned value (PV) = $70,000. How is the project going (choose the best possible answer)?
You are right on budget and ahead of schedule
Both your schedule and budget are better than planned
You are under-budget and ahead of schedule
You are over-budget but ahead of schedule