Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You have been tasked bythe management of Gusty Energy Inc.,with developing a logistics plan for the production and distribution of nacelles used in wind energy

You have been tasked bythe management of Gusty Energy Inc.,with developing a logistics plan for the production and distribution of nacelles used in wind energy production.Gusty Energy Incoperates using a 'Pull Business Model' and will run a production line to produce nacelles when they have orders for 250units. Today is5 June2023and the planned start date for production is5 September2023.When production starts,10nacelleswill be producedthe first business week and thereafter production will be30each business week and production will continue until 250nacellesare produced. Nacellesthat are produced need to be stored in the warehouse until they are shipped to the distributors(you can decide when to ship the completed nacelles).

The final product needs to be delivered in the following quantities to the following locations:

1)100 nacelles to Denver, Colorado

2)70nacelles to Panama

3)80nacelles to Chile

Components and materials

Generator:

Cylindrical in shape:48" long,24" in diameter

Weight-2500lbs.

Shipped in wood crate (crated by mfg)

There are two suppliers you can use. One is in Copenhagen Denmarkand the other is in theYen My II Industrial Zone and Industrial Park near Haiphong in Vietnam. You are free to choose either or both.

Origin: Copenhagen, Denmark(see Google earth photos)

Cost per unit $100,000

Time from order to production:45calendardays and then production will be15perworkday

Origin: Yen My II Industrial Zone and Industrial Park near Haiphong in Vietnam (see Google earth photos)

Cost per unit $75,000

Time from order to production:50calendar days and then production will be 10per workday.

Gearbox:

Rectangular in shape:24" high,24" wide,36" depth

Weight-900lbs.

Cost per unit $250,000

Packaged according to buyer's direction (buyer pays for materials)

Origin:Troy, Michigan

Time from order to production:45calendardays and then production will be5perworkday.

Nacelle Shell

Material: Composite (fiberglass,with aluminum frame members and steel mounting plate)

Weight-3,000lbs.

Packaged according to buyer's direction (buyer pays for materials)

Cost per unit- $10,000

Origin:Wilmington, Delaware

Time from order to production:40calendardays and then production will be5per workday

Electric Motors

Weights -Part 1-100lbs.

Part 2 -500lbs.

Packaged according to buyer's direction (buyer pays for materials)

Cost per unit- $15,000

Origin:Halifax, Nova Scotia, Canada

Time from order to production:45calendardays and then production will be20per workday

Controls:

24" high,12" wide,14" deep

Weight: 50lbs.

Packaged according to buyer's direction (buyer pays for materials)

Cost per unit- $1,000

Origin:Toronto, Canada

Time from order to production:30calendardays and then production will be10perworkday

Rotor: (aluminum casting)

3' 6" in diameter by 1' 6" in depth

Weight-200lbs.

Packaged according to buyer's direction (buyer pays for materials)

Cost per unit- $7,500

Origin:Toledo, Ohio

Time from order to production:45calendardays and then production will be20per workday

Steel:

Two-4' long shafts that are3" in diameter

Weight: each shaft weights340lbs.

Cost per shaft - $300

Packaged according to buyer's direction (buyer pays for materials)

Origin:Norfolk, Virginia

Time from order topick-upof each order:7calendar days

Pitch system and braking system (producedtogetherby one supplier)

Packaged in a crate by the supplier. Each crate contains one pitch system and one braking system)

Crate size: 48" by 24" by 18"

Weight:500lbs.

Cost per unit- $50,000

Origin:Columbus, Ohio

Time from order to production:30calendar days and then production will be5per workday

Misc:

Paint, welding wire, hoses and other supplies not mentioned previously can be locally sourced with three days' notice and will be delivered by the suppliers.The weight of all the miscellaneous items will total 75 lbs. per completed nacelle and would take up 3 cubic feet of space if stored. Cost per nacelle - $500

Cost of Warehousingonsite:

Cost $24square foot of floor space/per month ($12for any part of two weeks). This is an all-inclusive price (includes receiving, storage, and delivery to the assembly plant floor). Warehouse interior floor to ceiling height is 36'.

Assumptions:

a.General purpose 40' containers will be available at inland locations and 20', 40', 45' including high cube 40' and 45' containers will be available at the ports.53' truck trailers will be available for domestic transport.

b.All companies involved are well established, reputable, and profitable companies.

c.While you can use a 3PL you still need to address, in detail, each of the issues specified in the assignment. In other words, stating the 3PL will deal with the issue will not fly.

d.Currency exchange rates, bunker surcharges, and fuel surcharges will be based on today' date

e.A work week will start on Monday and end on Friday (5 days) and you do not need to factor in holidays.

  • Estimate the logistics costs involved and your justification for the tact taken. If you spent more in some portions of the logistics than the minimum possible, explain why (maybe you wanted to reduce risk)
  • Supporting calculations and references
  • Provide the total for the logistics costs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions

Question

3. Discuss the advantages of systems integration for UPS customers.

Answered: 1 week ago