You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project direct costs are given here.
You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here.
Activity | Immediate Predecessor | Normal Time | Crash Time | Normal Cost (Direct) | Crash Cost (Direct) | ||||
A | None | 3 | 2 | $300 | $400 | ||||
B | A | 3 | 3 | $100 | $100 | ||||
C | A | 1 | 1 | $200 | $200 | ||||
D | B and C | 3 | 2 | $400 | $550 | ||||
E | D | 2 | 1 | $500 | $900 | ||||
F | E | 3 | 3 | $200 | $200 | ||||
G | F | 2 | 2 | $100 | $100 | ||||
The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,
What is the total (i.e., direct and indirect) project cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started