You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project direct costs are given here.

You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here.

Activity Immediate Predecessor Normal Time Crash Time Normal Cost (Direct) Crash Cost (Direct)
A None 3 2 $300 $400
B A 3 3 $100 $100
C A 1 1 $200 $200
D B and C 3 2 $400 $550
E D 2 1 $500 $900
F E 3 3 $200 $200
G F 2 2 $100 $100

The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,

What is the total (i.e., direct and indirect) project cost?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions

Question

T F Packaging has little infl uence on buying decisions.

Answered: 1 week ago