You have decided to automate the processing of invoice reimbursements in your company. Your IT department has provided you with the following forecasts: Start date

You have decided to automate the processing of invoice reimbursements in your company.
Your IT department has provided you with the following forecasts:
Start date 01/04/2024
Project end date 12/05/2024
Development time 5 weeks
Testing and training 1 week
Cost of IT staff on project per week 10,000
Project launched as planned on 01/04/2024
Progress to 04/21/20243 weeks after start-up
of 30% for
at a cost of 31,500
The project ended on 02/06/20249 weeks after start-up
at a cost of 94,500
Calculate the total cost variance as at 04/21/2024
breaking it down into schedule variance and cost variance
Calculate the total variance at the end of the project 02/06/2024
breaking it down into time variance and cost variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sound Investing, Chapter 19 - Related-Party Transaction Ruse

Authors: Kate Mooney

1st Edition

0071719415, 9780071719414

More Books

Students also viewed these Accounting questions

Question

What are the purposes of promotion ?

Answered: 1 week ago

Question

Does it use a maximum of two typefaces or fonts?

Answered: 1 week ago