Activity Construction activities Predecessor Duration in days
A Buy materials
B Dig footings A
C Poor footings concrete B
D Flooring B
E Building the wall and plastering CD
F Roofing, window, and floor installations E
G Installation of electrical wire for lighting E
H Painting FG Required:
Develop an Activity on Node AON network diagram using the information in Table for the storeroom building project. Populate the network diagram by conducting a forward pass and backward pass. x marks
Based on the network diagram developed in : Indicate all the storeroom building project activity paths routes and calculate their durations. x marks
Identify the critical path of the building project and state two characteristics of a critical path? x marks
Identify two activities with a float and advise on the implication of a float on the identified activities on each activity. x marks
Draw tasks on a Gantt chart timeline based on your network diagram durations calculated in above. x marks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started