You have documented all possible risks that can affect your project with appropriate risk responses when they occur in your risk management plan. All other
You have documented all possible risks that can affect your project with appropriate risk responses when they occur in your risk management plan. All other remaining risks are called as: Group of answer choices Residual Risks Accepted Risks Risk Triggers Unmanageable Risks