You have just discovered an error in the implementation plan that will prevent you from meeting a milestone date. The BEST thing you can do

You have just discovered an error in the implementation plan that will prevent you from meeting a milestone date. The BEST thing you can do is:

Select one:

a. Develop options to meet the milestone date.

b. Change the milestone date.

c. Remove any discussion about dates in the project status report.

d. Educate the team about the need to meet milestones.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

General Aviation Marketing And Management

Authors: C. Daniel Prather

3rd Edition

9781575243016

More Books

Students also viewed these General Management questions

Question

Briefly explain the qualities of an able supervisor

Answered: 1 week ago

Question

Define policy making?

Answered: 1 week ago

Question

Define co-ordination?

Answered: 1 week ago

Question

What are the role of supervisors ?

Answered: 1 week ago