You have just taken over a project from another project manager. Incomplete information is available to you on the project status. You have been told

You have just taken over a project from another project manager. Incomplete information is available to you on the project status. You have been told that the cost performance index (CPI) = .92, the earned value (EV) = $322,000 and the planned value (PV) = $180,000. What is the actual cost (AC) for the project?

You are assigned to manage a 12 month project estimated to cost $36,000 at the end of the project. Today is the end of month 3 and you are 20% complete. According to the finance Department you have spent $7500 to date.

Calculate the PV, EV, and the AC

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Solution Given Information CPI 092 EV 322000 PV 180000 i A... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions