You have monitored cost budget and earned values for each activity or project What is the status of the project to date? 1 AC 65,000
You have monitored cost budget and earned values for each activity or project What is the status of the project to date?
1 AC 65,000 EV 62,000 BV 67,000
2 AC 85,000 EV 79,000 BV 89,000
3 AC 100,000 EV 102,000 BV 110,000
4 AC 125,000 EV 124,000 BV 123,000
5 AC 125,000 EV 123,000 BV 131,000
A The project ahead of schedule and under budget
B The project is behind schedule and under budget
C the project is ahead of schedule and over budget
D the project is ahead of shecule and under budget
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started