You have prepared the following schedule for a project in which the key resource is a tractor. There are three tractors available to the project.

You have prepared the following schedule for a project in which the key resource is a tractor. There are three tractors available to the project. The resource requirements are as shown in the diagrams below. Develop a resource-constrained schedule. Use the parallel method and heuristics given. Be sure to update each period as the computer would do.

Use the following order of heuristics: 1. Minimum slack, 2. Smallest duration, 3. Lowest identification number

Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project. "TP" stands for time period.

How long will the project take if it was NOT resource-constrained?

How long will the resource-constrained project take?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Statistics

Authors: Robert A. Donnelly

2nd Edition

0321925122, 978-0321925121

Students also viewed these General Management questions