Question

1 Approved Answer

You have prepared the following schedule for a project in which the key resource is a tractor. There are three tractors available to the project.

You have prepared the following schedule for a project in which the key resource is a tractor. There are three tractors available to the project. The resource requirements are as shown in the diagrams below. Develop a resource-constrained schedule. Use the parallel method and heuristics given. Be sure to update each period as the computer would do.

Use the following order of heuristics: 1. Minimum slack, 2. Smallest duration, 3. Lowest identification number

Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project. "TP" stands for time period.

How long will the project take if it was NOT resource-constrained?

How long will the resource-constrained project take?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

General Aviation Marketing And Management

Authors: Alexander T. Wells, Bruce D. Chadbourne

2nd Edition

1575241927, 978-1575241920

More Books

Students also viewed these General Management questions

Question

Solve each equation or inequality. |2x - 5 =9

Answered: 1 week ago