You have prepared the following schedule for a project in which the key resource is a backhoe ( s ) . This schedule is contingent
You have prepared the following schedule for a project in which the key resource is a backhoes This schedule is contingent on having three backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. page You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in months.
Develop a resource schedule in the loading chart that follows to see if it is possible to complete the project in months with only two backhoes. Be sure to record the order in which you schedule the activities using scheduling heuristics. Activities and require two backhoes, while activities and require one backhoe. No splitting of activities is possible. Can you say yes to Brookers request?Schedule the resource load chart with ES and slack updates
RES DUR
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started