Question

1 Approved Answer

You have prepared the following schedule for a project in which the key resource is a backhoe ( s ) . This schedule is contingent

You have prepared the following schedule for a project in which the key resource is a backhoe(s). This schedule is contingent on having three backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes. page 294You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in 11 months.
Develop a resource schedule in the loading chart that follows to see if it is possible to complete the project in 11 months with only two backhoes. Be sure to record the order in which you schedule the activities using scheduling heuristics. Activities 5 and 6 require two backhoes, while activities 1,2,3, and 4 require one backhoe. No splitting of activities is possible. Can you say yes to Brookers request?Schedule the resource load chart with ES and slack updates
ID RES DUR ESLFSL0,1,2,3,4,5,6,7,8,9,10,11,12,13
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions