You have project right now that costs $12,350 right now. A company is willing to take on the responsibility for the project, as long as
You have project right now that costs $12,350 right now. A company is willing to take on the responsibility for the project, as long as you pay them 25k, 15 years from now (at the end of the project). Your cost of capital is 5.60%. Which of these two is cheaper? How much cheaper (enter the absolute value below in the submission box). Are there any practical issues associated with this?