Question

1 Approved Answer

You have received revised estimates for the remaining activities at the end of the fourth quarter: 1. Prototypes will be completed on 3/8/11. 3. 2.

You have received revised estimates for the remaining activities at the end of the fourth quarter: 1. Prototypes will be completed on 3/8/11. 3. 2. Serial I/O drivers will be completed on 6/30/11. System hardware/software test will start on 7/1/11 and take 25 days. page 655 4. Order circuit boards will start on 8/8/11 and take 5 days. 5. Assemble preproduction model will begin on 10/14/11 and take 18 days. 6. Project documentation is expected to start on 8/8/11 and will take 55 days. 7. Network interface is expected to start on 8/8/11 and will take 99 days. 8. Shell is expected to start on 8/8/11 and will take 55 days. 9. Integrated acceptance testing is expected to start on 12/29/11 and will take 54 days. Prepare a memo that addresses the following questions: 1. What is the new EAC for the project? How long should the project take given these revised estimates? 2. How happy will top management be with these forecasts given the priorities of the project? 3. What recommendations would you make?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions

Question

What are the unique challenges to managing a virtual project team?

Answered: 1 week ago