Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working

You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 30 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 30 working days. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical activities.

ID Description Predecessor Time (days)
A Prepare site None 4
B Pour foundation A 3
C Erect frame B 5
D Roof C 3
E Windows C 3
F Doors C 5
G Electrical C 3
H Rough-in frame D, E, F, G 4
I Door opener F, G 2
J Paint H, I 1
K Cleanup J 6

How many days will the project take?

The early start on Activity D is how many days?

The late start on activity E is how many days?

The slack on Activity E is how many days?

The slack on Activity F is how many days?

Do you expect to receive a bonus or a penalty on this project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Linear Algebra A Modern Introduction

Authors: David Poole

4th edition

1285463242, 978-1285982830, 1285982835, 978-1285463247

Students also viewed these General Management questions