You have signed a contract to build a garage for the Simpsons. You will receive a$ 5 0 0 bonus for completing the project within
You have signed a contract to build a garage for the Simpsons. You will receive a$ bonus for completing the project within working days. The contract also contains a penalty clause in which you will lose $ for each day the project takes longer than working days. Draw a project network given the following information. Complete the forward and backward pass, compute activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?ID Description Predecessor Time A Prepare Site None B Pour Foundation A C Erect Frame B D Roof C E Windows C F Doors C G Electrical C H Roughin Frame D E F G I Door Opener F G J Paint H I K Cleanup J q You are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network, given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities. IID Description Predecessor Time days A System Design None B Subsystem A design A C Subsystem B design A D Subsystem C design A E Program A B F Program B C G Program C D H Subsystem A test E I Subsystem B test F J Subsystem C test G K Integration H I, J L Integration test K q K Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software Project. Note: Time is in daysID Description Predecessor Time A External specifications None B Review design features A C Document new features A D Write software A E Program and test B F Edit and publish notes C G Review manual D H Alpha site E F I Print manual G J Beta site H I K Manufacturer J L Release and ship K
You have signed a contract to build a garage for the Simpsons. You will receive a$ bonus for
completing the project within working days. The contract also contains a penalty clause in
which you will lose $ for each day the project takes longer than working days.
Draw a project network given the following information. Complete the forward and backward
pass, compute activity slack, and identify the critical path. Do you expect to receive a bonus or a
penalty on this project?ID Description Predecessor Time
A Prepare Site None
B Pour Foundation A
C Erect Frame B
D Roof C
E Windows C
F Doors C
G Electrical C
H Roughin Frame D E F G
I Door Opener F G
J Paint H I
K Cleanup J
q You are creating a customer database for the Hillsboro Hops minor league baseball team.
Draw a project network, given the information in the table that follows.
Complete the forward and backward pass, compute activity slack, and identify the critical path.
How long will this project take?
How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical
activities.
IID Description Predecessor Time days
A System Design None
B Subsystem A design A
C Subsystem B design A
D Subsystem C design A
E Program A B
F Program B C
G Program C D
H Subsystem A test E
I Subsystem B test F
J Subsystem C test G
K Integration H I, J
L
Integration test K
q
K Nelson, project manager of Print Software, Inc., wants you to prepare a project network;
compute the early, late, and slack activity times; determine the planned project duration; and
identify the critical path. His assistant has collected the following information for the Color
Printer Drivers Software Project.
Note: Time is in daysID Description Predecessor Time
A External specifications None
B Review design features A
C Document new features A
D Write software A
E Program and test B
F Edit and publish notes C
G Review manual D
H Alpha site E F
I Print manual G
J Beta site H I
K Manufacturer J
L Release and ship K
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started