You have the following three options for a new project. Given a discount rate of 12%, the correct order of PW, highest to lowest, is:
You have the following three options for a new project. Given a discount rate of 12%, the correct order of PW, highest to lowest, is:
A | B | C | |
First Cost: | -13,500 | -20,000 | -15,000 |
Annual MX Costs: | -1,500 | -1,800 | -1,100 |
Annual Revenue: | 9,500 | 11,000 | 9,000 |
Salvage Value: | 3,500 | 6,000 | 4,000 |
Time: | 5 | 5 | 5 |
answers:
A>B>C
B>A>C
C>A>B
C>B>A
Step by Step Solution