You manage a fabrication shop for granite and quartz slabs that are used in kitchen and bath remodels. You fulfill orders for several local contractors.

You manage a fabrication shop for granite and quartz slabs that are used in kitchen and bath remodels. You fulfill orders for several local contractors. You have almost finished the last pending job and you have new nine jobs that need to be scheduled. Like most businesses, you have several "customers." You need to do the work promptly for the contractors or they will stop using you. You also have to do timely work for the homeowners. You start with the jobs listed in the order that they were received. You have appraised the work and have estimated the time needed to do the work. The Due Date comes from the contractors, who have asked for each specific delivery date. That data is found in the table below:

Job ID Days needed Due Day
Romeo 15 3
Sierra 6 21
Tango 10 32
Uniform 7 44
Victor 5 43
Whiskey 3 51
X-ray 9 14
Yankee 12 49
Zulu 8 39

Please decide in what order to do the jobs. Use this data for the next questions:

1a) Using theShortest Processing Time scheduling rule, provide the order of the job. Please just provide the number.For example, if job Foxtrot should be done third, you would enter 3 in the blank after Foxtrot.

Romeo _

Sierra _

Tango _

Uniform _

Victor _

Whiskey _

X-ray _

Yankee _

Zulu _

1b) Using the First Come First Servedscheduling rule, provide the order of the job. Please just provide the number. For example, if job Foxtrot should be done third, you would enter 3 in the blank after Foxtrot.

Romeo _

Sierra _

Tango _

Uniform _

Victor _

Whiskey _

X-ray _

Yankee _

Zulu _

1c)Using theEarliest Due Date scheduling rule, provide the order of the job. Please just provide the number. For example, if job Foxtrot should be done third, you would enter 3 in the blank after Foxtrot.

Romeo _

Sierra _

Tango _

Uniform _

Victor _

Whiskey _

X-ray _

Yankee _

Zulu _

2a) Fill in the following grid. Use one decimal place for the Average Flow Time and Average Job Lateness and a whole number for the Number of Jobs late.

FCFS Rule SPT Rule EDD Rule
Average Flow Time
Average Job Lateness
Number of Jobs Late

2b)Which schedule would you choose, FCFS, SPT, or EDD and why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting

Authors: V. Rajasekaran, R. Lalitha

1st Edition

813173207X, 9788131732076

More Books

Students also viewed these Mathematics questions

Question

BPR always involves automation. Group of answer choices True False

Answered: 1 week ago