1 Approved Answer

You manage a project with 1 0 activities. Activities A 1 , A 3 , A 5 , and A 9 form the critical path.

You manage a project with 10 activities. Activities A1, A3, A5,
and A9
form the critical path. Because you have a large budget for the project, you consider crashing activity A2,
which has the potential to shorten the time of A2
by three days. What do you think about this opportunity?
multiple choice
It is a good idea because it will reduce the project duration by three days.
It is a bad idea because A2 is not on the critical path.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Applied Wildlife Habitat Management

Authors: Roel R. Lopez, Michael L. Morrison, Israel D. Parker

1st Edition

9781623495022

More Books

Students also viewed these General Management questions