You manage the production process in the high-tech facility of Dale Computers Inc. The facility produces two products (X&Y) - see Product Makeup & Annual

You manage the production process in the high-tech facility of Dale Computers Inc. The facility produces two products (X&Y) -see Product Makeup & Annual Demand table for details. The facility consists of three different assembly lines -see Assembly Capability & Capacity Table for details.

The production process begins with the procurement of raw materials from suppliers. Next, the raw materials are processed into six independent subassemblies, A-F, in separate work areas within the facility. Each product is then assembled on one of the assembly lines (see Subassembly & Post Assembly Capacity Table for sub-assembly details). Following assembly, each product is finished, customized (painted and other options added), packaged, and shipped. Current trends indicate that 20% of product X and 50% of product Y are customized.

Product Makeup & Annual Demand Table

Product Subassemblies for one unit of product Annual Unit Sales
X A= 2, B=1, C=1, E=1 52,000
Y B=1, C=1, D=2, E=2, F=1 52,000

Assembly Capability Table

Assembly Line Capability

Capacity

(Units / Week)

1 Either Product 1200
2 Product X 500
3 Product Y 600

Subassembly & Post Assembly Capacity Table

Subassembly Capacity (Units/Week)
A 2450
B 2280
C 2400
D 2450
E 3500
F 1200
Finishing 2500
Customizing 820
Packaging 3000

Question #1 (record letter & answer below)
Key business issue / why? =
Question #2
Product Product X Product Y Total If you cannot enter as %, enter as a ##.#
Demand XX.X%
Resource Product X Product Y Weekly Demand Capacity Utilization
Assembly Lines 0.0%
Subassembly A
Subassembly B
Subassembly C
Subassembly D
Subassembly E
Subassembly F
Finishing
Customizing
Packaging
Question #3
Product Product X Product Y Weekly Demand
Demand XX.X%
Resource Product X Product Y Weekly Demand Capacity Utilization Bottleneck #
Assembly Lines
Subassembly A
Subassembly B
Subassembly C
Subassembly D
Subassembly E
Subassembly F
Finishing
Customizing
Packaging
Question #4
Product Product X Product Y Weekly Demand
Demand XX.X%
Resource Product X Product Y Weekly Demand Capacity Utilization Bottleneck #
Assembly Lines
Subassembly A
Subassembly B
Subassembly C
Subassembly D
Subassembly E
Subassembly F
Finishing
Customizing
Packaging
Maximum System Throughput Total Weekly Units
If you could only invest in capacity for one resource, which one would it be and why? =

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cambridge IGCSE And O Level Additional Mathematics Coursebook

Authors: Sue Pemberton

2nd Edition

1108411665, 9781108411660

More Books

Students also viewed these Mathematics questions