You need to find out the maximum NPV of a hypothetical iron ore open pit as shown below. The iron ore grade is 72%

You need to find out the maximum NPV of a hypothetical iron ore open pit as shown below. The iron ore grade is 72% and recovery is 90%. The market price of iron ore is S100/ton. The ore and waste block size are 30 by 30 by 30 m3 and annul production of six blocks (mining + stripping) is there. The mining cost is $35/ton and the stripping cost is $25/ton. The density for the ore and waste is 4.5 ton/m and 2.5 ton/m respectively. Assuming initial investment $50 million the interest rate is 5% per year. W = waste;O = ore. W W WW W W W W WWW W W W WOW WOW W W W w WO ooW O W WW WOO0 WOO

Step by Step Solution

3.47 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

Volume of 1 block of ore and waste30303027000 m 3 Volume of 6 blocks of ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introductory Statistics

Authors: Prem S. Mann

8th Edition

9781118473986, 470904100, 1118473981, 978-0470904107

More Books

Students also viewed these Civil Engineering questions

Question

=+Based on this, what model might you use to predict Log10Price?

Answered: 1 week ago

Question

Explain the steps involved in training programmes.

Answered: 1 week ago

Question

What are the need and importance of training ?

Answered: 1 week ago