Question

1 Approved Answer

You run an custom t-shirt shop. You have a very specific process to make your t-shirts. First, you need to bleach the t-shirt, which takes

You run an custom t-shirt shop. You have a very specific process to make your t-shirts. First, you need to bleach the t-shirt, which takes 30 seconds. Then you add colors (done in any order) that take 10 seconds for red, 20 seconds for blue, and 15 seconds for yellow. After you finish all the coloring, you need to iron the shirt taking 90 seconds, and then finally fold the shit taking 79 seconds. If you run your business 12 hours a day, and you want to make the most number of shirts possible in a day, what is the efficiency of your optimal facility layout? Round your answer to the nearest percent, without the % symbol. For example, if your answer is 49.23%, enter 49 into the box.

Step by Step Solution

3.36 Rating (146 Votes )

There are 3 Steps involved in it

Step: 1

To maximize the number of shirts produced per day we need to minimize the time it takes to complete ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Statistics For Contemporary Decision Making

Authors: Black Ken

8th Edition

978-1118494769, 1118800842, 1118494768, 9781118800843, 978-1118749647

More Books

Students also viewed these Economics questions

Question

What factors contribute to distortions in memory?

Answered: 1 week ago