You share the vendor input about how the installation can be done in three days, and remind your team that you scheduled five plus have
You share the vendor input about how the installation can be done in three days, and remind your team that you scheduled five plus have an additional three days slack due to the parallel tasks 6.3 and 6.4. You spend three days working with the vendor to get more information then recalculate the schedule to give task 6.5 more time - even though it could extend the project end date