You want to estimate the duration of an activity on your project. Your pessimistic estimate is 10 days, your most likely estimate is 5 days,
You want to estimate the duration of an activity on your project. Your pessimistic estimate is 10 days, your most likely estimate is 5 days, and your optimistic estimate is 3 days. Using three point estimation, what is your duration estimate? a. 5.5 days b. 4.5 days c. 5 days d. 4 days