You want to plan for an item whose gross requirements are given in the following table. The lot sizing method is FOQ ( 2 0

You want to plan for an item whose gross requirements are given in the following table. The lot sizing method is FOQ (20), the leadtime is 1 week, the available on-hand inventory is 40 units, and the safety stock requirement is 10 units. There is a scheduled receipt of 20 units in Week 1.
Week 1 Week 2 Week 3 Week 4
Gross Requirements 402050
Scheduled receipts 20
Projected Available Balance
Planned Receipts
Planned Order Releases
(a) What is the projected available balance at the end of Week 1?
units
(b) What should be the planned receipt in Week2?
units
(c) What should be the planned order release in Week 3?
units

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology Conservation And Management

Authors: Anthony R. E. Sinclair, John M. Fryxell, Graeme Caughley

2nd Edition

1405107375, 978-1405107372

More Books

Students also viewed these General Management questions