Question

1 Approved Answer

you will be using the MSG software to enhance your previously submitted Project Schedule. It is therefore very important that you watch the MSG instructional

you will be using the MSG software to enhance your previously submitted Project Schedule. It is therefore very important that you watch the MSG instructional videos before attempting this assignment.

The following should be performed:

  • For each activity you enter the Start Date information as follows:
    • For those activities that should start on a specific date, directly enter this date into the Start Date field
    • For those activities that are dependent on the completion of prior activities, enter the dependency formula into the Start Date field
  • At least 50% of your activities must use dependency formulas
  • Consider your project to have progressed one month from the Schedule Start. Update the Progress field for the various activities that should either be complete (100%) or started (less than 100%)
  • Define at least eight (8) milestones and add them to your Project Schedule

Reminder: Do not update the End Date field (this is calculated automatically.

Phase 1: Initiating Phase

  • Work Package 1:Define project scope.
  • Activity 1: Review project requirements (Assigned To: You, Duration: 2 days, Progress: 0%)
  • Activity 2: Identify project stakeholders (Assigned To: You, Duration: 1 day, Progress: 0%)
  • Work Package 2:Establish project team.
  • Activity 1: Identify project roles and responsibilities (Assigned To: You, Duration: 1 day, Progress: 0%)
  • Activity 2: Assign team members to project roles (Assigned To: You, Duration: 1 day, Progress: 0%)

Phase 2: Planning Phase

  • Work Package 3: Research destinations and create itinerary.
  • Activity 1: Gather information about potential destinations (Assigned To: You, Duration: 5 days, Progress: 0%)
  • Activity 2: Evaluate and select destinations (Assigned To: You, Duration: 3 days, Progress: 0%)
  • Activity 3: detailed itinerary (Assigned To: You, Duration: 2 days, Progress: 0%)
  • Work Package 4: Plan transportation and accommodations.
  • Activity 1: Research transportation options (Assigned To: You, Duration: 3 days, Progress: 0%)
  • Activity 2: Book flights and other transportation (Assigned To: You, Duration: 2 days, Progress: 0%)
  • Activity 3: Research accommodation options (Assigned To: You, Duration: 3 days, Progress: 0%)
  • Activity 4: Book accommodations (Assigned To: You, Duration: 2 days, Progress: 0%)

Phase 3: Executing Phase

  • Work Package 5: Pack for the trip.
  • Activity 1: packing list (Assigned To: You, Duration: 2 days, Progress: 0%)
  • Activity 2: Pack essential items (Assigned To: You, Duration: 1 day, Progress: 0%)
  • Work Package 6: Complete pre-travel preparations.
  • Activity 1: Obtain necessary travel documents (Assigned To: You, Duration: 5 days, Progress: 0%)
  • Activity 2: Arrange for travel insurance (Assigned To: You, Duration: 2 days, Progress: 0%)

Phase 4: Closing Phase

  • Work Package 7: Review and document the trip.
  • Activity 1: Reflect on the experiences and highlights (Assigned To: You, Duration: 3 days, Progress: 0%)
  • Activity 2: Document the trip in a journal or blog (Assigned To: You, Duration: 5 days, Progress: 0%)
  • Work Package 8: Share the trip with others.
  • Activity 1: Create a photo album or slideshow (Assigned To: You, Duration: 3 days, Progress: 0%)
  • Activity 2: Organize a presentation or gathering to share the experiences (Assigned To: You, Duration: 2 days, Progress: 0%)

Company Name Schedule Start: Mon, 9-5-2022
Project Manager Display Week: 1
Work Week: 7 Day
ACTIVITY ASSIGNED TO DUR (days) PROGRESS START END
Phase 1 Title
N.NN Work Package Name
Task 1
Task 2
N.NN Work Package Name
Task 3
Task 4
Phase 2 Title
N.NN Work Package Name
Task 1
Task 2
N.NN Work Package Name
Task 3
Task 4
Phase 3 Title
N.NN Work Package Name
Task 1
Task 2
N.NN Work Package Name
Task 3
Task 4
Phase 4 Title
N.NN Work Package Name
Task 1
Task 2
N.NN Work Package Name
Task 3
Task 4
Phase 5 Title
N.NN Work Package Name
Task 1
Task 2
N.NN Work Package Name
Task 3 3 0%
Task 4 3 0%
Phase 6 Title
N.NN Work Package Name
Task 1
Task 2
N.NN Work Package Name
Task 3 3 0%
Task 4 3 0%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Quality Control And Improvement

Authors: Amitava Mitra

5th Edition

1119692334, 978-1119692331

More Books

Students also viewed these General Management questions

Question

4. Explain how to price managerial and professional jobs.

Answered: 1 week ago