You work as a project manager for you certified Inc. You have to enable roll ups of both resource assignments and availability data to a
You work as a project manager for you certified Inc. You have to enable roll ups of both resource assignments and availability data to a higher level. Which of the following diagrams will you use to achieve the task? A. Work breakdown structure B. Resource breakdown structure C. Roles and responsibility matrix D. Project network diagram