Question
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject "P" involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject "S" supplier specifications. These involve engineering details for how the product will perform.
The individual components that make up the product are the focus of subproject "D." Subproject "I" brings all the components together, and a working prototype is built and tested.
Finally, in subproject "V," suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
Major Subproject Activity Activity identification Dependency Duration
Product Specifications (P)
Market researchP1__1
Overall product specificationsP2P13
Hardware P3P23
Software P4P33
Supplier specifications (S)
HardwareS1P4 3
SoftwareS2P4 5
Product design (D)
BatteryD1S1 1
DisplayD2S1 1
CameraD3S1 1
Outer CoverD4D1, D2, D33
Product integration (I)
HardwareI1D44
User interfaceI2D23
Software CodingI3I23
Prototype Testing I4I1, I33
Product integration (I)
Supplier SelectionV1S1,S212
Contact negotiationV2I4, V12
Identify slack in the activities not on the project critical path.(Leave no cells blank - be certain to enter "0" wherever required.)
Activity ID Slack
P1
P2
P3
P4
S1
S2
D1
D2
D3
D4
11
12
13
14
V1
V2
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started