Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors

You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject P involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject S supplier specifications. These involve engineering details for how the product will perform.
The individual components that make up the product are the focus of subproject D. Subproject I brings all the components together, and a working prototype is built and tested.
Finally, in subproject V, suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)
Market research P12
Overall product specifications P2 P14
Hardware P3 P25
Software P4 P35
Supplier specifications (S)
Hardware S1 P45
Software S2 P48
Product design (D)
Battery D1 S11
Display D2 S12
Camera D3 S11
Outer cover D4 D1, D2, D34
Product integration (I)
Hardware I1 D42
User interface I2 D24
Software coding I3 I24
Prototype testing I4 I1, I34
Subcontracting (V)
Suppliers selection V1 S1,S212
Contract negotiation V2 I4, V12
a. Determine the minimum number of weeks for completing the project.
b. Your boss would like you to study the impact of making two changes to how the project is organized. The first change involves using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships within a subprojectall tasks within a subproject would be worked on at the same time and each would take the same amount of time as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V. What would be the expected impact on how long it would take to complete the project if this change were made?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Patrick J. Montana, Bruce H. Charnov

5th Edition

1438004826, 978-1438004822

More Books

Students also viewed these General Management questions