Question
You work for a telecommunications company and you have been appointed to a high priority project which will extend the mobile coverage in Northern Territory.
You work for a telecommunications company and you have been appointed to a high priority project which will extend the mobile coverage in Northern Territory. One of the key deliverables of the project is to install 50 highly customized antennas, which are special order and must be produced as per the unique design provided by your Design department. After consulting the Procurement department, you found out that you may procure antennas from only one supplier that won the bid of any special orders of your company for the next 5 years.
At the end of month 13th the seller reports 95% completion on deliverable. You check your baseline and the planned value at the end of the period is $4,512,000. You calculated the CV at the end of the period and the result is negative. How is the performance of the supplier?
Under budget, behind schedule
On time, on budget
On time, over budget
Over budget
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started