Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You work for ConstCo, a medium-sized engineering and construction company with annual profits of about $100 million. You recently entered as a contractor into a

You work for ConstCo, a medium-sized engineering and construction company with annual profits of about $100 million. You recently entered as a contractor into a bidding process for a large construction project. The total (projected) cost for the project will be about $500 million. The project will have a duration of 5 years, and the following estimated cost will occur throughout the five years (assume all cash flows occur at the end of a year):

Year 1: $200 million

Year 2: $100 million

Year 3: $100 million

Year 4: $50 million

Year 5: $50 million

Part A: The project is auctioned on a lump-sum turnkey contract, i.e. you as the contractor will receive a fixed payment for the project. Your sales manager is convinced that you can win the bidding process for a bid of about $650 million, with 20% being paid after the first year, 10% after years 2-4, and the final 50% being paid upon completion. Your finance department suggests using an interest rate of 15% for this project, since it represents considerable risks, like your client defaulting or actual costs being very different from your estimates. Calculate the Net Present Value for this project (see attached solution to part A).

Part B: Upon successfully bidding for the project (and obtaining the conditions specified in Part A), your client approaches you with an alternative arrangement. Instead of a lump-sum turnkey contract, they are willing to convert the project to a regular Engineering and Construction contract, where you bill the client for your cost. To align incentives, the client proposes that to ensure your profitability, they give you a 10% stake in the company that controls the project (called ManCo), a company that basically oversees construction, manages the facility afterwards and distributes the profits from the project to its owners. ManCo's CFO sees the current NPV of the project at $300 million, so your 10% stake of that would be worth $30 million. Your auditors have checked this estimate and consider it a fair value. But your auditors also warn you that there is considerable risk in this value - at the end of the project, ManCo may be worth as little at 10, or as much as 600 million dollars. Cost variations are a key reason for this risk. They expect that the probability distribution of the value of your stake in ManCo is a uniform one (i.e. equal probabilities) over all possible values from $1 to $60 million.

After some negotiations, your CEO is able to obtain a guarantee from ManCo that you can convert this 10% stake at any time for a $20 million lump-sum payout. For simplicity, assume that you would find out very quickly after signing the contract (i.e. within the first year) what the final value of your stake is.

Evaluate this alternative contract from a financial perspective. Should you consider this alternative contract? Besides your financial considerations, feel free to comment on other advantages and disadvantages you can see in this contract, and write a short (not more than half page) recommendation to your management team at ConstCo.

Must complete all steps:

QuestionGrading CriteriaPoints
A1Successfully calculate the correct series of Cash Flow10
A2Have the correct discount factor analysis10
A3Successfully calculate the correct amount of Present Value (PVs)10
A4Get the correct project NPV10
Subtotal40
B1Successfully calculate the correct series of Cash Flow20
B2Consider the project probability into the eNPV calculation10
B3Successfully calculate the correct Expected Value (EV)10
B4Successfully calculate the correct NPV10
B5Defend recommendation arguments10
Subtotal60
TOTAL100

Part A Solution: please crosscheck

image text in transcribedimage text in transcribed
Year FCF Outflow FCF Inflow Net FCF Discount Factor PV Supporting Data 200 130 -70 0.87 -60.87 Bid Amount 650 2 100 65 -35 0.76 -26.47 % paid year 1 0.2 3 100 65 -35 0.66 -23.01 % paid year 2-4 0.1 4 50 65 15 0.57 8.5763 % paid year 5 0.5 5 50 325 275 0.50 136.72 Interest Rate 0.15 NPV of Project 34.95

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ethical Decision-Making In The Hospitality Industry

Authors: Christine Jaszay, Christine Jaszay PhD, Paul Dunk

1st Edition

0131136801, 9780131136809

More Books

Students also viewed these General Management questions