Question

1 Approved Answer

You work for the Brads Nailer Company which manufactures two types of nailers: a pneumatic model and a cordless model. You have contracted to supply

You work for the Brads Nailer Company which manufactures two types of nailers: a pneumatic model and a cordless model. You have contracted to supply a national retail chain with both pneumatic nailers and cordless nailers; the minimum number of nailers is given below. However, Brads nailer production capability is limited in three departments: production, testing, and packaging. To minimize your costs, you have determined to ship more cordless nailers than pneumatic. (The number of nailers must be a whole number.)

Your answer will be the production hours needed to execute your production plan - rounded to the nearest whole hour.

Use Scenario 2

Scenario 1 Scenario 2 Scenario 3 Scenario 4
Pneum. Cost 52 55.50 38.50 79
Pneum. Prod Hrs 0.2 0.4 0.25 .4
Pneum. Test Hrs 0.3 0.3 0.4 .25
Pneum. Pkg Hrs 0.1 0.1 0.1 .15
Pneum. Sales 22,000 24,500 18,000 7,500
Cordless Cost 47 69.75 34 52
Cordless Prod Hrs 0.3 0.3 0.4 .4
Cordless Test Hrs 0.4 0.5 0.4 .3
Cordless Pkg Hrs 0.1 0.1 0.2 .1
Cordless Sales 15,500 15,500 14,000 5,000
Prod Hrs max 13,000 20,000 21,500 20,000
Testing Hrs max 17,000 21,000 18,000 17,000
Pkg Hrs max 4,500 5,500 5,500 5,500

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions