Question
YouhavesignedacontracttobuildagaragefortheSimpsons.Youwillreceivea$500bonusfor completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the
- YouhavesignedacontracttobuildagaragefortheSimpsons.Youwillreceivea$500bonusfor completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than working days.
Draw a project network given the following information. Complete the forward and backward pass,computeactivityslack,andidentifythecriticalpath.Doyouexpecttoreceive abonusora penalty on this project?
Garage
ID | Description | Predecessor | Time |
A | PrepareSite | None | 2 |
B | Pour Foundation | A | 3 |
C | ErectFrame | B | 4 |
D | Roof | C | 4 |
E | Windows | C | 1 |
F | Doors | C | 1 |
G | Electrical | C | 3 |
H | Rough-inFrame | D, E,F, G | 2 |
I | DoorOpener | F, G | 1 |
J | Paint | H,I | 2 |
K | Cleanup | J | 1 |
- YouarecreatingacustomerdatabasefortheHillsboroHopsminorleaguebaseballteam. Draw a project network, given the information in the table that follows.
Completetheforwardandbackwardpass,compute activityslack,andidentifythecriticalpath. How long will this project take?
Howsensitiveisthenetworkschedule?Calculatethefreeslackandtotalslackforallnoncritical activities.
ID | Description | Predecessor | Time(days) |
A | SystemDesign | None | 2 |
B | SubsystemA design | A | 1 |
C | SubsystemB design | A | 1 |
D | SubsystemC design | A | 1 |
E | ProgramA | B | 2 |
F | ProgramB | C | 2 |
G | ProgramC | D | 2 |
H | SubsystemA test | E | 1 |
I | SubsystemB test | F | 1 |
J | SubsystemC test | G | 1 |
K | Integration | H,I, J | 3 |
L | Integrationtest | K | 1 |
- K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; computetheearly,late,andslackactivitytimes;determinetheplannedprojectduration;and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software Project.
Note:Timeisindays.
ID | Description | Predecessor | Time |
A | Externalspecifications | None | 8 |
B | Reviewdesignfeatures | A | 2 |
C | Documentnewfeatures | A | 3 |
D | Write software | A | 60 |
E | Programandtest | B | 40 |
F | Editandpublishnotes | C | 2 |
G | Reviewmanual | D | 2 |
H | Alphasite | E, F | 20 |
I | Printmanual | G | 10 |
J | Beta site | H,I | 10 |
K | Manufacturer | J | 12 |
L | Releaseandship | K | 3 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started