Your boss, the chief financial officer ( CFO ) , has assigned you the task of evaluating 2 proposed capital renovation projects that Senior Executives

Your boss, the chief financial officer (CFO), has assigned you the task of evaluating 2 proposed capital renovation projects that Senior Executives are considering. You have received the following information to address questions on your assignment.
After-tax cash flows for the projects (in millions of dollars):
Year CFL CFS
0($30)($30)
1 $5 $20
2 $10 $10
3 $15 $ 8
4 $20 $ 6
1Plsfs. The firms tax rate =21%.
2. For bond financing: a) The current price = $1,035. on 1,000 par value bonds b) The coupon rate =8% with annual payment. c) The years to maturity =16 years. d) Flotation cost =0.
3. For preferred stock financing: a) The current price = $115 with a dividend rate =14% b) The par value = $100. c) Flotation rate =15%
4. For common stock financing: a) The current price = $50 per share. b) The current dividend (D0)= $4.19. c) Dividends are expected to grow at a constant annual rate =5%. d) Flotation cost =0 e) The company's beta =1.2 f) The yield on T-bonds =7%. g) The market risk premium =6%. h) Common shares outstanding =50,000.
5. The company's target capital structure is 10% debt, 20% preferred stock, and 70% common stock.
Q1: What is the before tax cost of debt?
Q2: What is the after tax cost of debt for the company?
Q3: What is the cost of preferred stock?
Q4: What is the cost of common stock using the Discounted Dividend Method approach?
Q5: What is the cost of common stock using the average of DDM and the CAPM?
Q6: What is the company's weighted average cost of capital?
Q7: Given the WACC that was calculated, what is the NPV of Project L?
Q8: Given the WACC that was calculated, what is the NPV of Project S?
Q9: What is the IRR of Project L?
Q10: What is the IRR of Project S?
Q11: Given the WACC that was calculated, what is the MIRR for Project L?
Q12: Given the WACC that was calculated, what is the MIRR for Project S?
Q13: The CFO thinks that the $0 flotation cost for bonds assumption may be incorrect based on a conversations with their banker. What would the after-tax cost of debt be with flotation cost = $30 per bond?
Q14: What is the payback period for Project L?
Q15: What is the payback period for Project S

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions